    CURRENT CAPITAL PROJECTS     (as of 10/27/09)

1. E Building Main Stage Sound, Video and Communication Systems
Consultant: Auerbach Pollock Friedlander
Contractor: Edart GTI, Inc.
Status: Project completed.

2. E Building Atrium Sound and Video Systems
Consultant: Auerbach Pollock Friedlander
Status: Project on Hold

3. Center 3 Façade Renovation
Architect: Fuller and D’Angelo, P.C.
Status: Project on Hold
 
4. Center 3 Fourth Floor Expansion
Architect: Helpern Architects
Engineer: Kallen & Lemelson
Construction Manager: URS Corporation
General Contractor: Citadel Construction Corp.
HVAC Contractor: R. Maric Piping Inc.
Plumbing Contractor: ARA Plumbing Inc.
Electrical Contractor: Danco Electrical Contractor Inc.
Status:Construction  completed.

5. Center 3  Admission and Bursar
Architect: APA Architects
Engineer: Kallen & Lemelson
Status: Design in progress
 
6. Center 3 New Elevators
Architect: APA Architects
Engineer: Kallen & Lemelson
Status: Construction in progress

7. Center 3 Elevator Lobbies
Architect: APA Architects
Engineer: Kallen & Lemelson
Status: Constuction in Progress

8. College-Wide Streetscape Improvement
Architect: Lee Weintraub Landscape Architecture, LLC
Status: Design in progress

9. Main Building Gymnasium Locker Room Improvement
Architect: Perkins Eastman
Engineer: Kallen & Lemelson
Contractor: Andy Handy Home Improvement
Status: Construction icompleted.

10. Main Building Solar Voltaic
Constuction Manager: New York Power Authority
Design Build Contractor: Fulcrum Group
Engineer: Saren Engineering Inc.
Status: Design in progress

11.Center 4 Parking Garage Demolition
Architect/Engineer: STV Inc.
Contractor: Gramercy Group Inc.
Status: Construction in progress.

12. Center 3  8th Floor and Infrastructure
Architect: Mitchell Giurgola
Engineer: Joseph Loring
Status: Design in progress

13. Main Building Black Box Upgrade
Architect: Steve Lepp Associates
Engineer: Athwal and Associates
Status: Design in progress

14. Main Building ECLC Project
Architect: Steve Lepp Associates
Contractor: Corbex
Status: Project Completed

15. Center 3 Cyber Cafe
Architect: Stephen Ely Associates
Status: Construction completed

16. E Building Biology Lab
Architect: Stephen Ely Associates
Engineer: Liker Engineering
Status: Bidding Review

17. Master Plan Study
Architect: Helpern Architects
Engineer: Kallen & Lemelson
Status: Master Plan was approved by Board of Trustees on Sept. 24, 2007; Project Completed
 
18.Center 3 Roof Replacement 
Architect: Superstructure Engineers + Architects
Construction Manager: AFG Construction Management, Inc.
Contractor: BQE 
Status: Started 10/05; Project completed

19.Center 3 Elevator Renovation
Architect/Engineer: J. Martin Associates
Construction Manager: AFG Construction Management, Inc. Contractor: Centennial Elevator
Status: Started 12/05; Project completed.